Project Schedule Summary

May 21, 2014 Kickoff Meeting
May 20 to August 4, 2014 Data Collection
June 4, 2014 Initial Public Open House #1
June 5 to November 12, 2014 Design Alternative Analysis
November 12, 2014 Public Open House #2 – Alternatives Presentation
November 12 to Fall 2015 Project Design
March 31, 2016 Public Meeting #3
May 23, 2016 Original Bid Date (Bids Rejected)
January 27, 2017 New Bid Date
April 2017 to December 2017 Construction
December 2017 Road re-opens to traffic
Dec 2017 – May 2018 Utility work continues with one way flagging
May 2018 – July 2018 Roadway reconstruction commences for Jackson and Long Lane with  one way flagging